A trimless finish uses a drywall L-bead instead of the factory trim to create a narrow, even gap around the FAKRO LST door.
This finish requires experience with attic ladder installation and drywall finishing. If needed, use a qualified installer.
The finished LST opening in a hallway ceiling.
The finished LST opening in a hallway ceiling.
Measure the outside dimensions of the LST frame before preparing the rough opening. The opening may be slightly smaller than the recommended size, but must allow room to position, shim, and secure the frame.
Use the measured frame and door dimensions to position the drywall L-bead. You can also temporarily position the ladder to mark its location. Support it as shown in the LST installation instructions, then remove it before finishing the drywall.
Skip Install the ladder from the attic for now and go to Fit the drywall L-bead. Once the ceiling finish is dry, return to Install the ladder from the attic.
Follow the sections below in order.
Do not install the included white metal factory trim.
If there is enough room in the attic, lower the assembled LST into the opening from above. Support it while positioning the frame. Square, level, shim, and secure the frame to the surrounding framing, then adjust the ladder to the ceiling height, following the LST installation instructions.
If you install the ladder before finishing the ceiling, mask the door to protect it from joint compound, primer, and paint.
LST installed before finishing the surrounding drywall.
Drywall edge alongside the LST frame.
LST installed before finishing the surrounding drywall.
Drywall edge alongside the LST frame.
Follow the steps below:
Continue with Finish the ceiling.
Drywall L-bead with a perforated flange for joint compound.
Checking the corner fit before attaching the drywall L-bead.
Drywall L-bead with a perforated flange for joint compound.
Checking the corner fit before attaching the drywall L-bead.
Feather the joint compound over the perforated flange of the drywall L-bead and out onto the ceiling. Once the joint compound is dry, sand, prime, and paint.
Keep joint compound and paint out of the gap around the door and off the gasket and moving hardware.
Joint compound applied over the drywall L-bead before painting.
The finished gap around the closed door.
Joint compound applied over the drywall L-bead before painting.
The finished gap around the closed door.
If you have any questions, our technical support team can help.
Copyright © 2026 FAKRO. All rights reserved.
| Monday | 8AM - 4PM |
| Tuesday | 8AM - 4PM |
| Wednesday | 8AM - 4PM |
| Thursday | 8AM - 4PM |
| Friday | 8AM - 4PM |
| Saturday | Closed |
| Sunday | Closed |
|
FAKRO America, LLC. 39 W Factory Rd, Addison, IL 60101 (630) 543-1010 |